Planning compatibility report in Spain: when you need it
What the planning compatibility report is in the Valencia region, when it is compulsory, deadlines and fees, with Alicante and Benidorm examples.
· 8 min read · Teciforp

A planning compatibility report (informe de compatibilidad urbanística) is the town hall's written answer to one question: does the use you have in mind — a restaurant, a clinic, a warehouse, a hotel — fit the zoning of that plot? In the Valencia region it is compulsory before you file the environmental permit for any business activity (Law 6/2014, art. 22). The town hall has one month to issue it, and a negative report is binding. Holiday lets need a different report, the tourist-use compatibility report (Law 15/2018, art. 65). And if what you want to know is how much you can build, the document is the cédula de garantía urbanística. If you are buying a building in Spain for a specific use, ask for the report before you commit: it is the cheapest way to rule out the wrong property.
Three documents people mix up
In practice, three different papers travel under the name "compatibility". Each answers a different question.
| Document | Question it answers | When it is compulsory | Town hall deadline | Effect |
|---|---|---|---|---|
| Municipal planning report or compatibility certificate (Law 6/2014, art. 22) | Can this activity operate on this plot? | Before any environmental permit: licencia ambiental, environmental declaración responsable or notice of a harmless activity | One month from the request (art. 22.3) | Binding if negative; it is not a building permit (art. 22.7) |
| Tourist-use compatibility report (Law 15/2018, art. 65.1) | Can this flat or house be let to tourists? | To register a holiday let (vivienda de uso turístico) and to renew it | Not set by law | No favourable report, no registration |
| Cédula de garantía urbanística or written planning information | What can be built here, and on what terms? | Optional, but gives certainty before design | One month under the Alicante and Benidorm ordinances | Locks in the conditions while valid |
The costly mistake is to treat the first one as permission to build, or to buy with the cédula in hand and assume the use is secured. They are parts of one puzzle.
How the activity report works under Law 6/2014
Who asks and when. The future operator asks the town hall before filing the environmental permit (art. 22.1). It applies to any activity, from a bar to a logistics warehouse.
What you attach (art. 22.2):
- A site plan of the plot (geo-referenced if the activity needs an integrated environmental authorisation).
- A description of the installation and the activity.
- The land use the activity needs.
- What the installation needs from public services: water, drainage, power, access.
What the town hall replies. A certificate signed by the council secretary and endorsed by the mayor, stating expressly whether the project is compatible (art. 22.4). It must cover land classification and zoning, permitted uses, planning changes in progress and, on rural land, whether a declaración de interés comunitario is needed (art. 22.3).
If they miss the deadline. The maximum is one month. After that you can file the permit simply stating the date of your request (art. 22.5); the law repeats this in the document list for the licencia ambiental (art. 53.2.1.c). For integrated authorisations you attach a copy of the request, and a later negative report ends the procedure (art. 22.6).
The private-verifier route. The duty does not apply to the licencia ambiental, the declaración responsable or the notice when you choose to have compliance checked by an accredited certification body (art. 22.1). The town hall may still check compatibility before granting the licence.
What it does not do. The report is separate from the planning permit (art. 22.7): it does not let you start works or open. The law sets no validity period, so if the process drags on and the zoning changes, ask for a new one.

Holiday lets: a separate report
Since Decree-law 9/2024, a holiday let only exists as such if it has a favourable tourist-use compatibility report from the town hall, or an equivalent document (Law 15/2018, art. 65.1). Registration lasts five years (art. 65.4). According to the regional government's FAQ (17/03/2026), renewal requires an up-to-date favourable report, and in towns that have suspended licences or changed their zoning the report may not be older than six months when you file.
Town halls may also cap the number of holiday lets per building, sector or area (art. 64 bis). If you are buying a flat in Spain to let to tourists, get the report before completion, not after. How holiday lets differ from aparthotels and hotels is covered in hotel, aparthotel or tourist flat.
How to apply in Alicante and Benidorm
Alicante. The city's licensing ordinance lists, among the reports issued by the planning department, the compulsory activity report and a joint compatibility and habitability certificate for tourist accommodation (art. 5.B). They are issued within fifteen working days of a complete file (art. 5.C). Companies and registered professionals must apply online (art. 2.B.2). You use form A09 with the cadastral reference; its annex sets a fee of €111.39 for the compatibility certificate but gives no year, so check the current rate. The planning department's service charter commits to issuing it in 15 days.
Timing matters: amendment no. 52 to Alicante's general plan (PGOU), which regulates tourist accommodation and is open for objections until 18 December 2026, includes a transitional regime for files with compatibility reports, according to the town hall's statement of 18 November. We explain it in opening a hotel in Alicante under the new rules.
Benidorm. The town's ordinance on planning and activity permits requires the compatibility certificate among the documents for opening bars, restaurants and other venues (art. 127.c). For shops, the town hall must issue it within one month, and the ordinance warns that silence does not mean the use is compatible (art. 104). Planning information and the cédula are covered in arts. 16–21, with one month to notify them from a complete request (art. 21.5).
When to ask if you are buying a building
Many foreign buyers receive the land registry extract and the energy certificate, but nobody has asked the town hall whether the intended use fits. A sensible order:
- Before the reservation: planning information or a cédula for the plot — zone, buildability, heritage protection.
- With a signed deposit contract (contrato de arras) and a condition precedent: the compatibility report for the exact use (hotel, restaurant, warehouse, holiday let), backed by a short description.
- In parallel: the technical survey of the building, explained in technical due diligence when buying a building.
- After completion: design, building permit or declaración responsable, and the environmental permit for the activity.
If the plan also requires a change of use of the building, the full route is in converting a building into a hotel in Alicante.
Checklist before you apply
- Cadastral reference and a site plan of the whole plot.
- A description of the activity, floor area, expected occupancy and installations.
- The exact use you need: "hotel" is not "tourist apartments", and "storage" is not "logistics".
- Service needs: electrical capacity, water, drainage and vehicle access.
- Municipal fee paid in advance; online filing if you apply through a company.
- The date of your request noted down — you will need it if the report is late.
This article is general information, not legal advice; check your case with the town hall or a Spanish lawyer. Facts checked on 24 November 2026.
If you are looking at a building or a plot on the Costa Blanca and want to know whether your project fits before you buy, call us on +34 602 510 710. We review the planning rules, prepare the description needed to request the report and survey the property, through our building search service.
Frequently asked questions
What is a planning compatibility report in Spain?
It is the town hall's certificate stating whether a specific activity or use fits the zoning of a plot. In the Valencia region it is governed by art. 22 of Law 6/2014 and is compulsory before the environmental permit of any business activity.
How long does the town hall take?
Law 6/2014 sets a maximum of one month. Alicante's ordinance sets fifteen working days from a complete file. If it is late, you can file the environmental permit stating the date of your request.
Does the report let me start building work?
No. The law states that it is separate from the planning permit. Works need a building permit or a declaración responsable, and the activity needs its own environmental permit.
What if the report is unfavourable?
A negative report is binding: the activity cannot be set up on that plot with that use. In an integrated environmental authorisation, a negative report received during the process ends it.
Do I need it to let a flat to tourists?
Yes, but it is a different report: the tourist-use compatibility report required by art. 65 of Law 15/2018 to register the property. When you renew the five-year registration you need an updated one.
How much does it cost in Alicante?
Form A09 states a fee of €111.39 for the compatibility certificate, without a reference year. Check the current tax ordinance before paying.
Sources
- Law 6/2014 of 25 July of the Generalitat on Prevention, Quality and Environmental Control of Activities, consolidated text (last amended 13/11/2026), arts. 22 and 53: boe.es
- Law 15/2018 of 7 June on tourism, leisure and hospitality of the Valencia region, consolidated text, arts. 64 bis and 65: boe.es
- Generalitat Valenciana, FAQ on holiday lets, 17/03/2026: cindi.gva.es
- Alicante City Council, ordinance on planning and environmental licences, chapter 2, arts. 2–7: normatia.com
- Alicante City Council, form A09 for written planning information and the municipal planning report: alicante.es
- Alicante City Council, planning department service charter: alicante.es
- Alicante City Council, statement on amendment no. 52 to the PGOU, 18/11/2026: alicante.es
- Benidorm Town Council, ordinance on planning and activity permits, arts. 16–21, 104 and 127: contenidos.benidorm.org