A hotel renovation in Benidorm that adds no floor area does not need a full building licence, even if it touches the structure or the façade. It goes through a self-certified declaration (declaración responsable): once it is filed complete, you can start work. If you extend the building, you need a major works licence (licencia de obra mayor), which the town hall must decide within two months. If you want more rooms or larger rooms using the extra floor area of Benidorm's "hotel incentive" rules, an Internal Reform Plan (Plan de Reforma Interior, PRI) has to be approved first and the licence comes after. The local building tax (ICIO) is 4% of the construction cost. Two council rules set the calendar: no works between 22:00 and 08:00 or on public holidays, and no works in the town centre that occupy the street with scaffolding or heavy lorries in July, August or Easter week. In practice, the heavy façade work fits between October and mid-March.
Everything below comes from the ordinances and planning documents published by Benidorm town hall (Ayuntamiento de Benidorm). A summary of the local rules is on our Benidorm page.
Which permit your Benidorm hotel renovation needs
Benidorm's ordinance on planning and activity permits sorts works by two questions: does the work extend the building or create a new one, and does it affect anything listed? The size or budget of the renovation does not decide the permit.
| What you plan to do in the hotel | Permit | Timeline | Where it says so |
|---|---|---|---|
| Interior refurbishment that leaves structure and listed elements alone: bathrooms, finishes, room services | Declaración responsable (with a sketch or technical documents, depending on the work) | Start once filed complete | Ordinance, arts. 23 and 26.2 |
| Full renovation affecting structure, façade or external appearance, without extending | Declaración responsable with a technical project, structural calculations if the structure is affected, and the site architect's acceptance | Start once filed complete | Ordinance, arts. 23 and 26.1 |
| Extension: more floor area, storeys or volume | Major works licence with a project | Two months for a decision | Ordinance, arts. 32.a and 38 |
| Extension using the extra floor area of the hotel incentive rules | PRI approved first, then a major works licence | PRI time plus two months | PGMO amendment no. 1 and the amendment no. 25 document |
| Any work on a protected, listed or soon-to-be-listed building | Licence | Depends on the work | Ordinance, art. 31.1.j |
| Change of use (cambio de uso), for example from apartments to hotel | One licence covering both the use and the works | Depends on the work | Ordinance, art. 162 |
Two points that often surprise foreign owners:
- A declaración responsable is not a light formality. For structural work it requires a project by a qualified architect or engineer, endorsed by their professional college where Royal Decree 1000/2010 requires it (ordinance art. 26.1). Spain's Building Act, the Ley de Ordenación de la Edificación (LOE, art. 2.2.b), already requires a project for full interventions on existing buildings. If the town hall later finds that the work needed a licence, it opens proceedings to restore planning legality.
- The project must meet the Building Code where you intervene. Spain's Technical Building Code (Código Técnico de la Edificación, CTE, Part I, art. 2) applies to works on existing buildings. If full compliance is not feasible, the designer justifies it in writing, and the works must never leave the building worse than before.
Companies deal with Spanish public bodies electronically: Law 39/2015 (art. 14.2) obliges legal entities to do so. In Benidorm, permits are filed through the town hall's online portal (sede electrónica), Urbanismo section. If you hold the hotel through a Spanish company (S.L.), your architect or representative will need its digital certificate or a power of attorney.
Before any design work, ask for the planning information or the planning guarantee certificate (cédula de garantía urbanística) for the plot. The ordinance gives the town hall one month to issue it once the complete request is registered (art. 21.5). It tells you the zone, whether the building is protected and how much room the plan leaves you.
More rooms or larger rooms: the hotel incentive route
Benidorm is governed by its 1990 General Municipal Plan (Plan General Municipal de Ordenación, PGMO), which has had 22 specific amendments and 9 official interpretations; the consolidated text of its planning rules was approved by the full council on 31 January 2022. For hotels, the key piece is amendment no. 1, "Incentivación hotelera". According to the initial strategic document for amendment no. 25 (4 March 2026), its history is:
- Amendment no. 1, approved by the regional minister on 20/07/2001 and published in the provincial gazette (BOP) on 12/01/2002.
- First update, approved on 23/04/2015 and published in the BOP on 23/06/2015.
- Second update, approved by the council on 31/07/2017 and published in the BOP on 05/09/2017.
- Third update (amendment no. 25), in progress in March 2026, with a stated aim: moving four-star hotels up to five stars.
The incentive lets four- and five-star hotels enlarge their rooms without the increase counting towards the zone's maximum floor area. In exchange, the hotel provides compensation to keep the area's level of public facilities, and that requires a PRI to be drafted and approved before the licence. When the town hall started six of these PRIs in February 2020, it described the compensation like this: two linear metres of frontage to widen the pavement and, if that is not enough, land for public use or cash. Approved PRIs are published on the council website, such as the one for the Primavera Park hotel (document dated 8 February 2022).
A PRI is a planning procedure, with environmental assessment and public consultation, and has no two-month deadline like a licence. If your renovation depends on that extra floor area, the PRI sets your start date. Also check whether amendment no. 25 has been approved by the time you design.

What you pay the town hall: ICIO tax and the permit fee
Benidorm's Tax Ordinance no. 5 (consolidated text, BOP 20/05/2021) sets the construction, installations and works tax (Impuesto sobre Construcciones, Instalaciones y Obras, ICIO) at 4% (art. 7). That is the maximum allowed by Spain's Local Finance Act (art. 102.3). The tax base is the material construction cost (coste de ejecución material): VAT, fees, professional fees and the contractor's profit are excluded (art. 102.1). The tax falls due when work starts (ordinance art. 9).
| Material construction cost of the renovation | ICIO at 4% |
|---|---|
| €500,000 | €20,000 |
| €1,500,000 | €60,000 |
| €3,000,000 | €120,000 |
| €6,000,000 | €240,000 |
Three details that change the figure:
- Provisional assessment. It is issued when the licence is granted or the declaración responsable is filed. The ordinance includes a reference-budget method based on floor area and use (art. 11), and once the work is finished the town hall can adjust the base to the real cost.
- Reliefs. The only one in the ordinance (art. 10) is 95% for works declared of special interest in buildings for essential public services such as health, education or social services. A hotel renovation does not qualify.
- Permit fee. On top of the ICIO you pay the fee under Tax Ordinance no. 11, which sets the fee for planning permits and related procedures. Check the current rate on the online portal before you finalise the budget.
How to fit the works into the low season
In Benidorm the works calendar is set by council ordinances, not only by hotel occupancy.
Working hours. Noise Ordinance no. 3 (BOP no. 77, 16/04/2007) bans construction work between 22:00 and 08:00 on working days and all day on public holidays. Equipment may not exceed 90 dB(A) measured at five metres, and the noisiest tasks must be done between 10:00 and 20:00, taking into account nearby homes, hotels and hospitals (art. 26). Loading and unloading of materials is banned from 22:00 to 08:00 (art. 27).
Summer and Easter. Annex III.1 of the ordinance on planning and activity permits, which governs works on public roads, states that works in the town centre that directly affect the street, such as putting up scaffolding or heavy lorry traffic, will not take place in July, August or Easter week (Semana Santa). Exceptions exist: in June 2021, according to Alicante Plaza, the town hall authorised 22 works by decree to continue through the summer, including the structural strengthening of a hotel. Still, it is unwise to plan around an exception.
While the site is open. The same annex requires approved hoarding around the whole perimeter, covered walkways to the entrances of homes, hotels and shops in busy pedestrian areas, and 24-hour supervision of the site protections, especially at weekends and on peak tourist dates. A permit to occupy the public road is obtained before work starts.
With those rules, a sensible calendar for a hotel that closes in winter looks like this:
| Period | What to do |
|---|---|
| Spring and summer | Survey with the hotel open (structure, services, façade), planning information and design project |
| September | Declaración responsable filed complete or licence granted; contract and health and safety plan signed |
| October to mid-March | Scaffolding, façade, roof, structure and main services: everything that occupies the street |
| Before Easter week (in 2027, 21 to 28 March) | Take the scaffolding off the street; carry on with interiors and finishes |
| April to June | Rooms floor by floor, testing of services and handover documents |
If the hotel stays open, the works go floor by floor or tower by tower, with site routes kept apart from guests. We explain the stages up to opening in hotel construction phases.

The stages of the renovation and the document that closes each one
- Survey. Condition of structure, roof, façade, services and fire safety. Closed by a technical report listing defects and what must be fixed.
- Planning check. Planning information or certificate (one month, art. 21.5) and, if you want extra floor area, a decision on the PRI. Closed by a feasibility report stating the permit you need. The numbers behind it are covered in our hotel feasibility study guide.
- Project. Basic and detailed design, justifying the CTE where you intervene. Closed by the project and, where required, the college endorsement (visado).
- Permit. Declaración responsable filed complete or licence granted; provisional ICIO assessment.
- Contract and site set-up. Contract with scope, price and programme fixed, health and safety coordination and plan (Royal Decree 1627/1997, arts. 3 and 7) and the street occupation permit. We compare contract models in turnkey fixed-price contract.
- Works and close-out. Phased works, final completion certificate and handover record (acta de recepción). The LOE guarantee periods run from handover (art. 17).
Checklist before you sign the renovation
- Planning information confirms the zone and that the building is not listed.
- You know whether the works extend the building and, if you need the incentive, you have the PRI.
- The project states whether it affects the structure and includes structural calculations.
- The budget includes ICIO at 4% and the Tax Ordinance no. 11 fee.
- The programme keeps scaffolding and lorries out of July, August and Easter week.
- If the company owns the hotel, its digital certificate or a power of attorney is ready for online filing.
This article is general information. It is not legal advice and does not replace checking your case with Benidorm town hall. Information checked on 17 November 2026.
If you own a hotel in Benidorm and want to renovate it in full, call us on +34 602 510 710. We work from our office in Alicante: we look at which permit the works need, what you will pay in local taxes and which months they fit into, and we run it with a single point of responsibility. What we do on these projects is on our hotel construction and renovation page.
Frequently asked questions
Does renovating a hotel in Benidorm need a major works licence?
Only if you extend, build new or demolish, or if the building is listed. A full renovation without extension, even one that touches the structure or the façade, goes through a declaración responsable with a project (arts. 23 and 26 of the municipal ordinance).
How long does Benidorm town hall take to grant a major works licence?
The ordinance sets two months for a decision (art. 38). If the renovation needs the extra floor area of the hotel incentive rules, a PRI must be approved first. That is a planning procedure and takes considerably longer.
How much is the ICIO building tax in Benidorm?
4% of the material construction cost, under Tax Ordinance no. 5 (art. 7). For example, on a renovation with a material cost of €1,500,000 it comes to €60,000. The permit fee under Tax Ordinance no. 11 comes on top.
Can you carry out works in a Benidorm hotel in summer?
The noise ordinance does not ban private works in summer, but it limits working hours. Works in the town centre that occupy the street with scaffolding or heavy lorries are excluded in July, August and Easter week (Annex III.1 of the permits ordinance), unless expressly authorised.
What is a hotel incentive PRI?
An Internal Reform Plan that lets a four- or five-star hotel enlarge its rooms without the increase counting towards the zone's floor area limit, in exchange for compensation: frontage for the pavement, land for public use or cash. It is approved before the licence is applied for.
Can a foreign company file the permit itself?
Yes, through the town hall's online portal. Spanish law requires legal entities to deal with public bodies electronically (Law 39/2015, art. 14.2), so the company needs a digital certificate or a representative with a power of attorney.
Sources
- Benidorm town hall, Ordinance on planning and activity permits (Ordenanza de autorizaciones urbanísticas y de actividades), arts. 21, 23, 26, 31, 32, 38, 162 and Annex III.1: contenidos.benidorm.org
- Benidorm town hall, Tax Ordinance no. 5 on ICIO, consolidated text (BOP 20/05/2021), arts. 7, 9, 10 and 11: contenidos.benidorm.org
- Benidorm town hall, Tax Ordinance no. 11, fee for planning permits: contenidos.benidorm.org
- Benidorm town hall, Municipal Ordinance no. 3 on noise and vibration (BOP no. 77, 16/04/2007), arts. 26 and 27: contenidos.benidorm.org
- Benidorm town hall, initial strategic document for PGMO amendment no. 25 (third update of the hotel incentive rules), 04/03/2026: contenidos.benidorm.org
- Benidorm town hall, start of six hotel PRIs, 28/02/2020: benidorm.org
- Benidorm town hall, PRI for the Primavera Park hotel, 08/02/2022: contenidos.benidorm.org
- Benidorm town hall, online portal (sede electrónica): sede.benidorm.org
- Royal Legislative Decree 2/2004, Local Finance Act (texto refundido de la Ley Reguladora de las Haciendas Locales), art. 102: boe.es
- Law 39/2015 on common administrative procedure, art. 14: boe.es
- Law 38/1999, Building Act (LOE), arts. 2 and 17: boe.es
- Royal Decree 314/2006, Technical Building Code, Part I, art. 2: boe.es
- Royal Decree 1627/1997, health and safety on construction sites, arts. 3 and 7: boe.es
- Alicante Plaza, "Benidorm permitirá 22 obras en verano", 25/06/2021: alicanteplaza.es