A new hotel in Alicante city centre has entered the permit process: the city council has opened public consultation on the environmental licence (licencia ambiental) for a hotel at Plaza Ruperto Chapí 3, opposite the Teatro Principal, in the building that used to house the Chamber of Commerce. The notice for file A01-2026000025 was signed by the council's deputy secretary on 16 November 2026 and allows 20 working days for comments. This is an application, not a granted licence, and the notice gives no room count, star rating or investment figure.
What has been published, and who is applying
The notice on the council's official noticeboard (tablón de edictos), issued by the planning department, contains four facts: activity "hotel establishment" (establecimiento hotelero), location Plaza Ruperto Chapí no. 3, applicant Triana Team Coop. V. (a Valencian cooperative), and installations "as per technical project". The file can be inspected at the Urban Planning Information Office (Oficina de Información Urbanística, Plaza del Ayuntamiento 5), and comments must be filed in writing at the council's General Register. The legal basis is article 55.1 of the Valencian Law 6/2014 on environmental prevention, quality and control of activities.
According to the local daily Información (17 Nov 2026), the Chamber rented the building until last December, the owners then put it up for sale, and the applicant is a recently formed cooperative from Sant Joan d'Alacant that specialises in small accommodation. These details are not in the official notice.
Where the application stands
Public consultation comes after the council's formal check of the documents (art. 54). Under Law 6/2014 the remaining steps are:
| Step | What happens | Legal time limit |
|---|---|---|
| Public consultation (art. 55.1) | Notice on the noticeboard and council website; anyone may comment | At least 20 days |
| Neighbours' hearing (art. 55.2) | Personal notification to adjoining neighbours | At least 10 days |
| Sector reports (art. 56) | Whatever other regulations require for the activity | As set by each regulation |
| Environmental assessment (dictamen ambiental, art. 58) | In towns of 50,000+ residents, by the council's technical panel or an accredited body | — |
| Applicant's hearing (art. 59) | Before the draft decision | 10 to 15 days |
| Decision (art. 60) | Grant or refusal | 6 months from application |
| Start-up (art. 61) | Notice with a technician's certificate; council inspection | 1 month for the inspection |
If the project involves building works, article 53.3 requires them to be processed together with the environmental licence. The regional government's Decree-Law 9/2026 (DOGV, 13 Nov 2026) has just amended Law 6/2014, but not these articles or the hotel threshold.

What a new hotel in Alicante city centre tells investors
First, the procedure. The law requires an environmental licence for hotels with more than 1,500 m² of built floor area or an evacuation height above 28 metres (Annex II, section 13.2.7); below those thresholds a self-certified environmental declaration (declaración responsable ambiental) is generally enough. Because this file is going through the licence route, the project either exceeds one of those thresholds or falls under another Annex II case. The notice does not say which.
Second, the building type. This is an office building in the centre switching to hotel use, the route we explain in our guide to converting a building into a hotel in Alicante. Heritage protection matters a great deal. In April 2026 the planning department refused the licence to turn the former Ideal cinema into a hotel, because the project gutted a protected building and kept only its facades.
Third, the market. According to Información, citing the hotel association Hosbec's third-quarter monitor, Alicante has 166 hotel establishments with 10,448 bed places, about 63 per establishment, against 99 in Valencia and 335 in Benidorm. These are press figures that we have not been able to check against the Hosbec report.
What to do now if you are looking for a hotel building
- Before buying, ask for the municipal planning report (informe urbanístico municipal, art. 22 of Law 6/2014). It confirms whether hotel use is allowed on that plot.
- Check the heritage catalogue (Catálogo de Protecciones). The protection level decides whether you can reconfigure floors or only refurbish.
- Measure the building against the 1,500 m² threshold. It tells you whether you face an environmental licence (up to 6 months) or a self-certified declaration.
- Check the neighbourhood caps on tourist beds the city is preparing. We summarise them in opening a hotel in Alicante under the new tourism rules.
- Run the numbers for the whole deal with a hotel feasibility study before you sign.
This article summarises public rules and notices; it is not legal advice.
If you are considering converting a building in central Alicante into a hotel, call us on +34 602 510 710. We will go through the building, the procedure and the works with you. More on our hotel construction and renovation page.
Frequently asked questions
Does the Plaza Ruperto Chapí hotel already have a licence?
No. The notice of 16 Nov 2026 opens public consultation on the environmental licence application. The decision comes after reports, the environmental assessment and hearings; the law allows six months from the application.
Who can comment, and how?
Any person or organisation that considers itself affected, in writing at the council's General Register, within the 20 working days set in the notice. Adjoining neighbours are also notified personally.
How many rooms will the hotel have?
Not known. The notice gives no room count, category or investment, and the press has not reported them either.
Does every hotel in the Valencia region need an environmental licence?
No. Only those above 1,500 m² of built floor area or 28 metres of evacuation height, among other Annex II cases in Law 6/2014. Smaller hotels generally use the self-certified environmental declaration.
Sources
- Alicante City Council, Planning. Notice for file A01-2026000025, "establecimiento hotelero", Plaza Ruperto Chapí no. 3, signed 16 Nov 2026.
- Law 6/2014 of 25 July on environmental prevention, quality and control of activities in the Valencian Community, consolidated text (BOE): arts. 22, 53, 55, 56, 58–61 and Annex II, 13.2.7.
- Decree-Law 9/2026 of 6 November of the Consell, DOGV no. 10493, 13 Nov 2026.
- Alicante City Council. Urbanismo deniega la licencia de obra a un hotel en el Ideal por su protección, 20 Apr 2026.
- Información, 17 Nov 2026. La antigua sede de la Cámara de Comercio frente al Teatro Principal se convierte en hotel