Alicante council opposes El Plantío golf resort expansion
Alicante's council has issued an unfavourable report on the El Plantío golf resort expansion. The region decides: what was flagged and what it means.
· 6 min read · Teciforp

Alicante City Council has turned against the El Plantío golf resort expansion. On Tuesday 17 November 2026 its governing board (Junta de Gobierno Local) approved a second planning report on the scheme, this time unfavourable, and agreed to send it to the Valencian regional government, according to Alicante Plaza (18.11.2026). The report is mandatory but not binding: the decision on whether the scheme becomes a Project of Regional Interest (Proyecto de Interés Autonómico, PIA) lies with the regional cabinet (Consell). We have found no official council statement or published text of the resolution yet; this article relies on press reports and on the law.
What the council decided
Alicante Plaza, which says it has seen the report, describes a reversal of July 2025, when the same board backed the scheme with conditions. The objections now, as reported:
- A car park planned on specially protected rural land, protected because it is a dry riverbed (rambla).
- Building coverage above the maximum allowed on ordinary rural land (suelo no urbanizable común).
- Ancillary golf buildings in regular use by people, which should sit outside the riverbed.
- Unresolved road access: Camino de Agua Amarga would need widening to about 30 metres and Camino de Colmenares has to be defined.
- No measures yet on flood risk, sewerage and water supply, or on protecting the Camino Botiguera track.
Deputy mayor Manuel Villar said the document is neither final nor binding, and that the council would report favourably if the developer resolves these points. English-language weekly The Leader carries the same account.
The El Plantío golf resort expansion in figures
These are figures published by Alicante Plaza from the planning file; we have not been able to check them against the original documents.
| Item | What has been published |
|---|---|
| Developer | El Plantío Golf Resort, S.L. |
| Planned investment | €118–150 million |
| Site | From 554,483 m² today to about 1.18 million m² |
| New uses | Second 18-hole golf course, five football pitches, 12 padel courts, indoor sports hall, international school, student residence and 53 tourist villas |
| Land | Rural land not zoned for building (suelo no urbanizable): part ordinary, part specially protected riverbed, according to the paper |
| Jobs | 213 new posts, according to the developer |
The file already holds two favourable reports from regional departments (strategic projects and sport). On 13 October the regional directorate for planning, landscape and environmental assessment issued the scoping document for the environmental impact study: the developer must prove the water supply and study flood risk, and the document lapses after two years if the study is not filed.

Why a negative council report does not end the scheme
In Spain, building normally depends on the municipal plan and a municipal licence (licencia de obra). The PIA is a regional fast track for large investments that can override that plan. It is governed by articles 63 to 66 quater of the Valencian planning act, the consolidated Law on Spatial Planning, Urbanism and Landscape (TRLOTUP), as in force since July 2026:
- Where it can go. Anywhere in the region except Natura 2000 sites, whatever the land classification. On protected rural land the Consell decides after weighing the submissions of the municipality and the sector authority (art. 63.2).
- What is required. Productive investment above €50 million and a significant number of permanent jobs (art. 63.3).
- The council's role. A 15-day hearing once the application is admitted (art. 65.4). The act does not say its view is binding.
- What the declaration does. It carries direct planning compatibility for the project, whatever the land classification (art. 66.2). Rural land is not reclassified (art. 63.7), and the municipality folds the project into its plan at the next revision (art. 63.8).
- What it does not guarantee. The declaration does not prejudge viability and lapses after four years without final authorisation (art. 66.3). The developer lodges a guarantee of 5% of the investment, capped at €2.5 million (art. 65.5), and must keep the activity going for ten years (art. 63.10).
The El Plantío file was opened before the latest amendments to these articles; which wording applies to it is not stated in what has been published.
Who is affected and what to do now
Anyone planning a hotel, resort, sports complex or private school on rural land in Alicante province. Three practical lessons:
- Before you buy land, check what stalled this report: classification and protection of each plot, riverbeds, the real width of access roads, and where water and sewerage connect. This is the work we do in our building and plot search service.
- Water is proven with a concession, not a forecast. The scoping document asks for the concession and for annual, monthly and daily consumption figures.
- The regional route does not bypass the town hall. Its submissions weigh on the Consell's decision, and the works still need licences afterwards (arts. 66 bis and 66 ter). Build that risk and those timings into your feasibility study.
This same week Alicante has put its rules on new tourist beds in the city back out to public consultation with stricter limits; see opening a hotel in Alicante under the new rules.
This article summarises press reports and public legislation; it is not legal advice.
If you are weighing up a hotel or tourism project in Alicante and want to know what the land allows before committing money, call us on +34 602 510 710. More on our hotel construction and renovation page.
Frequently asked questions
Has the El Plantío expansion been refused?
No. The council's report is unfavourable but not binding. Declaring the scheme a Project of Regional Interest is for the Consell, and the file remains in environmental assessment, according to Alicante Plaza.
Can the regional government approve a project that does not fit the municipal plan?
The law allows it: a PIA declaration carries direct planning compatibility whatever the land classification (art. 66.2 TRLOTUP), and the plan follows the Consell's resolution (art. 63.8). On protected rural land the Consell must first weigh the municipality's submissions (art. 63.2).
What can the developer do now?
According to the deputy mayor, if access, flood risk and utility connections are resolved, the council would report favourably. The developer must also file the environmental impact study with the water supply proven.
Is there an official text of the report?
As of 18 November 2026 we have found no council statement or published resolution. If one appears, we will update this article.
Sources
- Alicante Plaza, 18.11.2026. Report on the governing board's unfavourable report on the El Plantío expansion (in Spanish).
- The Leader, 18.11.2026. Alicante reverses its support for the El Plantío expansion.
- Alicante Plaza, 01.11.2026. Scoping document for the environmental assessment: water and flood risk (in Spanish).
- Alicante Plaza, 01.10.2026. Favourable reports from two regional directorates (in Spanish).
- Alicante Plaza, 20.05.2026. Project description, areas and land classification (in Spanish).
- Alicante Plaza, 21.07.2025. First council report, favourable with conditions (in Spanish).
- Legislative Decree 1/2021, consolidated Law on Spatial Planning, Urbanism and Landscape of the Valencian Community, consolidated text (BOE, in Spanish): arts. 63 to 66 quater.