Hotel energy-renovation grants open in the Valencia region

IVACE has €22.3m for energy renovation of hotels and commercial buildings in the Valencia region. Rates, rules and deadline, as presented in Benidorm.

· 6 min read · Teciforp

Mid-rise Mediterranean hotel with scaffolding on one wing, new façade insulation and newly fitted windows

Energy-renovation grants for hotels, offices, shops and clinics in the Valencia region have been open since 12 November 2026. The regional business agency IVACE has €22.3 million for existing non-residential buildings (the PREE Terciario programme): up to 30% of the cost, 40% for medium-sized companies and 50% for small ones, with applications accepted until 30 June 2027 in order of arrival. On Tuesday 17 November the hotel association HOSBEC and the Hotel Technology Institute (ITH) presented the scheme to hoteliers in Benidorm, with a figure of their own: the energy renovations they have tracked save more than €120,000 a year per hotel on average.

What happened

In Benidorm, on 17 November 2026. HOSBEC and ITH closed their ITH Hotel Energy Meetings 2026 tour at the Gran Hotel Bali, with the regional director general for tourism, Israel Martínez, taking part, according to elperiodic.com. According to Diario de Alicante and Radio Sirena, the average results of the ITHSaveHotel programme were presented and HOSBEC's president, Fede Fuster, urged hoteliers to apply. We found no official HOSBEC release with these figures: they are press reports.

Average per hotel (ITHSaveHotel) Figure
Investment about €878,000
Annual saving more than €120,000
Energy no longer consumed 760,200 kWh a year
Emissions avoided about 202 t of CO₂ a year
Payback period 7.6 years

The call. It is IVACE's Resolution of 22 October 2026, published in the regional official gazette (DOGV) no. 10491 of 11 November 2026; the rules (bases reguladoras) date from 11 September 2026 (DOGV no. 10452 of 16 September 2026). Spain's energy agency IDAE links to all three official texts. The money comes from the National Energy Efficiency Fund: the PREE Terciario programme shares €200 million among Spain's regions, which run the calls.

Which buildings and works qualify for the energy-renovation grants

According to the summary of the call published by FEMPA, Alicante's metal-industry federation, and the regional government's announcement as reported by elperiodic.com:

  • Buildings: existing, built before 2014, located in the Valencia region, with more than 500 m² of usable floor area. A whole building, a single unit or part of a building can qualify.
  • Uses: hotels, guesthouses and residences; offices; shops; healthcare and education buildings; restaurants and bars; cultural, sports, transport and religious buildings.
  • Works: the thermal envelope (façades, roofs, glazing and external joinery); heating, cooling and hot-water systems using renewables (air-source heat pumps, solar thermal, geothermal, biomass); lighting; building automation and control.
  • Minimum results: at least a 20% cut in final energy consumption and at least a 20% improvement in primary energy efficiency, shown where applicable by the energy performance certificate (certificado de eficiencia energética) before and after, with eligible costs above €10,000.
  • Excluded: extensions, changes of use (cambio de uso), fossil-fuel boilers, cogeneration and district heating or cooling. Solar panels for electricity do not count on their own as a final-energy saving.
Flat roof of a Mediterranean hotel with newly installed heat pumps and solar thermal collectors

How much the grant covers

The basic grant is up to 30% of eligible costs, plus 10 points for medium-sized companies and 20 for small ones. Summaries of the rules published by The Officer and the Rincón de Ademuz association of municipalities add two top-ups: 5 points in assisted areas and 15 if the primary-energy improvement reaches 40%. Check the rules before counting on them.

As an order of magnitude, taking the average ITHSaveHotel investment and assuming every euro were eligible:

Company size Grant rate Grant on €878,000
Large 30% €263,400
Medium 40% €351,200
Small 50% €439,000

This is our own sum, not a figure from the call: not every item is eligible and the rules may set caps.

The rule that costs most applicants their grant

Work must not start before the application is registered. According to FEMPA, "starting" includes beginning work on site, placing a firm order for equipment or making any commitment that makes the investment irreversible; a supplier's invoice or a payment dated before the application puts the grant at risk. Preparatory costs such as the design, technical reports and the energy certificate are accepted if incurred after 1 January 2026. Once the application is registered you may start without waiting for the decision, but with no guarantee of an award.

What to do now if you own a hotel or commercial building here

  1. Commission the current energy certificate and the design now: they show whether you reach the 20%. Do not sign the building contract or order equipment until the application is registered.
  2. Separate the budget lines: in a full building renovation only the energy part is eligible; extensions and changes of use are not.
  3. Apply early: grants go in order of arrival until the €22.3 million runs out; after that there is only a waiting list. Applications are filed online only, through IVACE.
  4. Fit the calendar: works must be finished within 18 months of the award, extendable to 24, according to The Officer. For a hotel in Benidorm that allows the work to be spread over one or two low seasons.

This article summarises public information about a grant call; it is not legal or tax advice.

If you plan to renovate a hotel, a building or commercial premises or offices and want the works to fit this grant, call us on +34 602 510 710: we will go through the building, the design and the timetable with you. More on our hotel construction and renovation page.

Frequently asked questions

Until when can hotels apply for the IVACE grant?

Until 30 June 2027. The window opened on 12 November 2026, the day after the notice appeared in the official gazette, and grants are awarded in order of submission while the budget lasts.

Can I apply if the works have already started?

Not for anything already started or committed. A firm order, an invoice or a payment dated before the application is registered breaks the so-called incentive effect. Only preparatory costs incurred after 1 January 2026 are safe.

Does a renovation that extends the hotel or changes the building's use qualify?

No. Extensions and changes of use are excluded. If your project includes them, ask IVACE first how to separate the energy works.

Sources

Call us

Planning a project like this? Call us.

In one call we tell you whether we can take on your project, what is needed to start and what the next steps are. Complete projects only: we do not do partial renovations or one-off jobs.

+34 602 510 710

WhatsApp

We speak English, Spanish and Russian

Monday to Friday, 9:00–14:00 and 17:00–19:00

We'll call you

Leave your number and we'll call you

We speak English, Spanish and Russian · Monday to Friday, 9:00–14:00 and 17:00–19:00

Data controller: Teciforp S.L. · Purpose: to call you back about your request · Your rights: info@teciforp.es

CallWhatsAppWe'll call you